Markdown and editors soft-wrap on their own, so the manual ~75-char line breaks across the docs added nothing but noise. Join wrapped prose, list items, and paragraphs into single lines across 67 docs — README, CLAUDE.md, deployment, usage, the RAG knowledge base, and the agent role prompts. Whitespace-only: code fences, tables, and blockquote alerts are byte-identical and the change is token-verified (no content altered). Applied with a deterministic reflow tool (committed separately). Also lands two doc edits that were awaiting commit: the measured under-load resource numbers in usage.md and the pr_reviewer additions to the org-structure RAG doc.
4.0 KiB
Task Planning Workflow
Overview
Planning is a PM activity. When a PM (Cell PM or Main PM) picks up a coordination or parent task, they record a plan with i_will_plan and then fan the work out into subtasks with delegate.
triage / give_me_work → i_will_plan → delegate (one per subtask) → i_am_idle
Developers do not have a separate planning verb — they pass a short plan argument directly to i_will_work_on(task_id, plan="...") when they claim a coding task.
Submitting a Plan (PM)
i_will_plan(
task_id="<task>",
plan="One-paragraph summary of how this work will be broken down",
approach="High-level implementation strategy",
sub_tasks=[
"UX/UI: design the settings panel",
"Frontend: wire the panel to the API",
"Backend: add the settings endpoint",
],
technical_considerations=["Reuse the existing config service"],
risks=["Frontend depends on the UX design landing first"],
open_questions=["Confirm the default toggle state with the CEO"],
)
After i_will_plan, the envelope's next field points you at delegate — create one subtask per unit of work:
delegate(
parent_task_id="<task>",
title="Add the settings endpoint",
description="...",
assigned_to="be-dev-1",
team="backend",
task_type="code",
nature="feature",
estimated_complexity="medium",
acceptance_criteria=["Endpoint returns 200 with the saved settings"],
covers_parent_criteria=["<parent-ac-id>"],
)
Acceptance-Criteria Coverage
When you decompose a parent task, declare which parent criteria each subtask is responsible for with covers_parent_criteria (a list of the parent's acceptance_criteria_ids). This is what lets the org prove a decomposition covers the parent's full intent — and it drives two gates and your coverage briefing.
After i_will_plan and after each delegate, your envelope carries a coverage view of the parent so you can see what is still unmapped:
parent_ac_coverage— one entry per parent criterion: itsid,text, whether a live subtaskclaimedit, and whether a completed subtaskverifiedit.unclaimed_parent_acs— the parent criterion ids that no live subtask covers yet. Keep delegating until this is empty.
Two gates build on the coverage link:
- Decomposition floor — you cannot go
i_am_idleon a parent while a criterion is still unclaimed. Delegate (orreassign) subtasks until every criterion is covered. - Roll-up gate — a parent cannot
complete,submit_up, orescalate_to_ceounless every criterion traces to a child that passed QA on it.
Both gates are safe-by-construction: they stay inert until you start declaring covers_parent_criteria, so a decomposition that never declares coverage is never blocked. Declaring coverage is how you opt your parent into the guarantee.
Delegating Code Work: Per-Dev Queues
For code subtasks, delegate each developer their full queue up front rather than one task at a time. Both of a cell's developers build in parallel, and each works its own queue one task at a time, in order:
- A per-lane dispatch barrier holds a developer's later subtasks until their current one is in flight — so each dev's lane stays sequenced while the two devs run concurrently.
- Leaf PRs are still merged into the shared cell branch in sequence, not in parallel.
- Order the queue by dependency: the subtask others build on goes first.
Caps still apply: at most 12 subtasks per parent, and same-title duplicate subtasks are rejected.
Git Workflow
All code tasks follow the git workflow:
- Branches are auto-created when a developer claims the task via
i_will_work_on— no manual branch creation - Root tasks: branch created from the default branch (main/master)
- Subtasks: branch forked from the parent's branch
Coordination/parent tasks that only plan and delegate (no code) do not need a branch of their own.
Hierarchical branch naming uses -- between task IDs to avoid git ref conflicts: feature/{team}/{ROOT}--{SUB}--{SUBSUB}.