# BMM Solutioning Workflows (Phase 3)
**Reading Time:** ~8 minutes
## Overview
Phase 3 (Solutioning) workflows translate **what** to build (from Planning) into **how** to build it (technical design). This phase is **required for Levels 3-4** and **optional for Level 2** projects.
**Key principle:** Prevent agent conflicts by making architectural decisions explicit and documented before implementation begins.
---
## Phase 3 Solutioning Flow
```mermaid
%%{init: {'theme':'base', 'themeVariables': { 'primaryColor':'#fff','primaryTextColor':'#000','primaryBorderColor':'#000','lineColor':'#000','fontSize':'16px','fontFamily':'arial'}}}%%
graph TB
FromPRD["<b>FROM Phase 2</b><br/>PRD/GDD/Narrative/UX complete"]
subgraph Solutioning["<b>PHASE 3: SOLUTIONING</b>"]
direction TB
Architecture["<b>Architect: architecture</b><br/>Technical design and decisions"]
GateCheck["<b>Architect: solutioning-gate-check</b><br/>Validation before implementation"]
end
subgraph Optional["<b>OPTIONAL PATHS</b>"]
direction LR
Level2Skip["<b>Level 2:</b><br/>Skip if straightforward"]
end
FromPRD --> Architecture
Architecture --> GateCheck
GateCheck -->|PASS| Phase4["<b>Phase 4: Implementation</b>"]
GateCheck -->|CONCERNS/FAIL| Architecture
FromPRD -.->|Level 2 only| Level2Skip
Level2Skip -.-> Phase4
style FromPRD fill:#e1bee7,stroke:#6a1b9a,stroke-width:2px,color:#000
style Solutioning fill:#90caf9,stroke:#0d47a1,stroke-width:3px,color:#000
style Optional fill:#fff9c4,stroke:#f57f17,stroke-width:3px,color:#000
style Phase4 fill:#ffcc80,stroke:#e65100,stroke-width:2px,color:#000
style Architecture fill:#64b5f6,stroke:#0d47a1,stroke-width:2px,color:#000
style GateCheck fill:#64b5f6,stroke:#0d47a1,stroke-width:2px,color:#000
style Level2Skip fill:#fff59d,stroke:#f57f17,stroke-width:2px,color:#000
```
---
## Quick Reference
| Workflow | Project Levels | Duration | Purpose |
| -------------------------- | -------------- | --------- | ------------------------------------------- |
| **architecture** | 2-4 | 2-6 hours | Technical architecture and design decisions |
| **solutioning-gate-check** | 3-4 | 15-30 min | Validate planning/solutioning completeness |
| Workflow | Project Levels | Purpose |
| -------------------------- | -------------- | ------------------------------------------- |
| **architecture** | 2-4 | Technical architecture and design decisions |
| **solutioning-gate-check** | 3-4 | Validate planning/solutioning completeness |
**When to Skip Solutioning:**
@@ -86,11 +123,6 @@ Collaborative architectural decision facilitation that produces a decision-focus
**Phase:** 3 (Solutioning)
**Project Levels:** 2-4
**Required:** Level 3-4, Optional Level 2
**Typical Duration:**
- Level 2: 1-2 hours (Simple architecture)
- Level 3: 2-4 hours (Standard architecture)
- Level 4: 4-8 hours (Complex architecture with ADRs)
### When to Use
@@ -341,7 +373,6 @@ Systematically validate that all planning and solutioning phases are complete an
**Phase:** 3 (Solutioning)
**Project Levels:** 3-4
**Required:** Level 3-4 only
**Typical Duration:** 15-30 minutes
### When to Use
@@ -544,21 +575,20 @@ Optional:
1. **Critical**: Architecture missing security architecture section
- **Impact**: Epic 1 (Auth) and Epic 4 (Checkout) lack security guidance
- **Recommendation**: Complete security architecture (2 hours)
- **Recommendation**: Complete security architecture
2. **High**: Payment gateway not selected
- **Impact**: Epic 4 (Checkout) cannot proceed
- **Recommendation**: Add ADR for payment gateway selection (1 hour)
- **Recommendation**: Add ADR for payment gateway selection
3. **Medium**: Epic 2, Story 3 too large
- **Impact**: Risk of story scope creep
- **Recommendation**: Split into 2 stories (30 min)
- **Recommendation**: Split into 2 stories
**Gate Decision:** CONCERNS ⚠️
- **Rationale**: Critical and high gaps block Epic 1 and Epic 4
- **Action**: Resolve gaps #1 and #2 before starting implementation
- **Timeline**: Address in 3 hours, then re-run gate check
**Next Steps:**